You are here : Home > The Project > Schedule for building

Appendix 1

Building Schedule for West Clare Canoe


Phase 1 – 38 hours

First week will set up workshop, purchase materials and prepare for start of course.
· Hand Selection and purchase of good timbers - 2 day
· Making steaming pipe for shaping ribs – ½ day
· Build plug for shaping ribs -1 day
· Build Stand – ½ day
· Preparing facility and setting up workshop -1 day

Phase 2 – Making component parts - 24 hours

· Course orientation and taking measurements of Cully’s Boat
· Mortise frames – 4 hours
· Cut Bow Frames – 1 hours
· Mortise Bow Frames – 2 hour
· Shape nose piece – 1 hour
· Shape Tackings – (14) – 4 hours
· Shape rungs – 4 hours
· Shape knees- 3 hours
· Cut Strewn Frames – 1 hour
· Cut Seats and chamfer – 1hour

Phase 3 - Assemble all components made – 8 hours

· Assemble top frame work and tackings -1 hour
· Assemble stern -1 hour
· Assemble bow – 1hour
· Install seats 1 hour
· Install knees – 3 hours
· Treat all work with Cuprinol - 1 hour

Top frame completed



Phase 4 – Prepare liurachs and ribs – 13 hours

· Turn canoe upside down and secure to building frame
1 hour
· Treat all mortise holes again with Cuprinol -1 hour
· Prepare ribs; cut to length and soak in clean water - 2 hours
· Cut wedges – 4 hours
· Cut Liurachs – 4 hours
· Install building moulds – 1 hour

Phase 5 - Fit liurachs and ribs – 20 hours

· Steam ribs and strap onto plug -3 hours
· Remove ribs from plug and install in canoe – 3 hours
· Secure with wedges -3 hours
· Install Liurachs and clinch nails -1 day
· Treat all work again with Cuprinol - 2 hours
· Release canoe form building frame and remove building moulds –1 hour

Phase 6 – Mouldings, rowlocks, timbels and footsteps – 10 hours

· Turn currach back right way up and prepare moulding and rowlocks, timbels and footsteps - 6 hours
· Install rowlocks, footsteps and timbles -4 hours

Phase 7 – Final primer and paint for timber frame –9 hours

· Prime all woodwork with aluminium primer - 3 hours
· Undercoat and finish coat all timber – 6 hours
·
Phase 8 – Prepare canvas – 21 hours

· Turn boat upside down and measure canvas -1 hour
· Prepare leather canvas for 1 boat
This will be researched and proposal will be put forward as to whether we will cure hide ourselves or purchase leather. Extra cost will be met by the club.
· Sow canvas -1 day
· Apply tar to canvas – 1 hour
· Flip and tack canvas to gunnels – 3 hours
· Apply 3 coats of tar -1 day

Phase 9 - Oars, cleats and toule pins - 16 hours

· Shape oars - 6 hours
· Shape cleats -1 hours
· Shape toule pins - 1 hours
· Prime, undercoat and finish coat oars -1 day

Phase 10 – Applying what is learned

· Repair old canoes in the area with skills learnt during the course.
Materials to be provided by Currach Club





Schedule for building



Phase Oct/Nov Dec Jan Feb Mar April May
1 - 2 ****** *******
3 -4 ****** *******
5 -6 ****** ********
7 -8 ******* ****
9 ****** ******* *
10 ** ** ** ** ** **




Materials - Schedule for building


 
West Clare Currach Club, Dunlickey Road, Kilkee, Co Clare, Ireland.
Phone : +353 087 6744550 E-mail: info@westclarecurrachs.com

 
National developement plan    European Union structural funds    Leader Group    
This project has been part funded through LEADER NRDP

RRD is not responsible for the content of this website

 

Privacy Statement | Sitemap
powered by SitesToGo TM